Reader Interactions
Comments
Trackbacks
-
[…] one final piece of advice I have. Find out as much as you can about burndown charts. Though they’re no longer a part of the official Scrum Guide, I found that there were three […]
-
[…] Burndown charts. I read through those tips to be aware of them, but didn’t get any questions concerning this domain. However, I recommend e.g.https://turboscrum.wpengine.com/2012/05/burndown-chart/ […]
-
[…] one final piece of advice I have. Find out as much as you can about burndown charts. Though they’re no longer a part of the official Scrum Guide, I found that there were three […]
-
[…] ou mais perguntas no exame que exigem este conhecimento. Leia sobre gráficos burndown aqui e […]
-
2017-02 – PSPO 1 Certification
Exam The Professional Scrum Product Owner (PSPO) l
-
Copy of 2017-02 – PSPO 1 Certification
Exam The Professional Scrum Product Owner (PSPO) l
-
Study Guide for PSPO I Certification
Exam The Professional Scrum Product Owner (PSPO) l
-
[…] Scrum beschreibt keine konkreten Praktiken, dennoch wird in der Prüfung Wissen zu Burndown charts vorausgesetzt. […]
-
[…] Read about Burndown Charts hereand here. […]
-
[…] about Burndown Charts here and […]
-
[…] about Burndown Charts here and […]
-
[…] about Burndown Charts here and […]
-
[…] Read about Burndown Charts here and here. […]
-
[…] Burndown Charts. […]
-
[…] Burndown Charts. […]
-
[…] about Burndown Charts here and […]
Chandra says
Nice article…i am interested to know your thoughts on how the burn down chart handles the newly added story points.
Derek says
Hi Chandra
You’ve hit at the major problem of the simple burndown chart right there. There have been a number of attempts to improve the basic burndown chart but they suffer from two major issues. Firstly, Scrum isn’t concerned with how long something took, just how much work is remaining. Secondly, any adjustment to the burndown chart makes reporting more complicated.
With that said, Mike Cohn at Mountain Goat software has written an article on alternative Burndown Charts. I’m rather partial to the first alternate he proposes.
Govindaraj Anand says
Hi Derek,
Good article… Thanks for sharing this. Looking for more detailed one with different assumptions.
Derek says
Hi Anand
It’s been on my mind to add some more detail to this article. It was originally conceived to provide help to those wishing to sit the PSM I assessment. In that regard, it’s great. However, in terms of burndown charts themselves, it could certainly stand some extra detail.
John Paul says
I thought Development Team does not estimate remaining ALL stories to assign points, and in practice not beyond 2 Sprint (immediate next sprint) and partial (following to next sprint) as complete clarity might not be available.
In that sense I do not think Burn Down Chart provides valuable information.
Should Development Team assign Estimation point as soon as user story hits Backlog to have a right burn down chart?
admin says
Hi John Paul
You’re right when you say that Development Teams usually produce fine-grained estimates for the next one to two sprints only. However, because relative size estimation is so easy, it’s not uncommon for Development Teams to estimate all of the items in a backlog so that the Product Owner can maintain a Release Burndown Chart or a Product Roadmap. That’s what this article refers to.
For Sprints, the Development Team will probably maintain a Sprint Burndown Chart where they might plot remaining task hours versus remaining days.
Burndown Charts exist only if the Scrum Team see value in them,
Yan Simkin says
Hi Derek, John Paul,
RE: “it’s not uncommon for Development Teams to estimate all of the items in a backlog ”
So even to draw Burn Down chart it is necessary to estimate full backlog like in this article it is 250 at the first Sprint.
Then why Scrum Guide never mention this step as it would be of utmost importance?
I have not seen Dev team taking a task to estimate(user-point-groom) 20 sprints worth of PBI-s but only maybe up to 3 sprints and not sure this task would fit under limit of 10% of Dev team capacity .
This seems as a lot of waste to refine and point that much since many PBI-s would be dropped or changed during 20-sprint period
So is it really uncommon for Dev team to point ahead of time for 20 sprints?
webgate says
Hello Yan
You may be mixing a couple of ideas here.
Firstly, Scrum says very little about estimating other than that it must be done by the team that will do the work. Story points, like relative size estimating, are a technique that you can choose to apply on top of Scrum. Hence why the Scrum Guide never mentions this.
Secondly, estimating Product Backlog Items (PBIs) doesn’t require that all PBIs are fully described. You may just have a title on a card and, for now, give it the estimate ‘100’. A quick and simple technique albeit less accurate. Teams I work with do this all the time.
I agree your assertion that only the next 2 to 3 Sprints worth of work should be broken down and suffuciently detailed to be taken into a Sprint.
Kim Nguyen says
Thank you Derek for the nice explanation of Burndown chart, but I believe that an iteration is equivalent to a sprint, and there is no Sprint named 0. Correct me if I am wrong.
webgate says
Hello Kim
The terms iteration and sprint are often used interchangeably. However, in scrum, we always talk about a sprint.
Sprint 0 is often used to describe preparatory activities such as choosing the environment, infrastructure, architecture, etc.
However, the purpose of a sprint is to produce a potentially releasable product increment. A sprint would never consist only of preparatory items of work. Hence why the term is often disliked.
Venkataraman says
hi,
I have a question – the article says that the burn down chart doesnt tell you about change in requirements. Lets say 10 story points are added then shouldnt the graph slope downward by equivalent of 10 story points as opposed to being flat. The team has anyway burned down 10 story poonts right?
webgate says
Hello
In fact, the chart will slope upwards because you have added more work.
When I say that the chart doesn’t tell you about a change in requirements, I mean that you cannot infer anything from the chart about whether work was added or removed. For example, if a chart is flat, it might indicate that no work was done or, that work equal to the amount done was also added. The chart won’t indicate which of those circumstances is true. It simply indicates the amount of work remaining.
Nasser says
Thank you , very nice article …so interested
Zail Singh says
Not sure of your last para title “One final thought …” in the article.
Shouldn’t adding an extra 10 story points to the product backlog also increase the Y axis length hence reflecting the true picture of progress in the new chart?
If 10 story points are existing to the total count in product backlog then adding it to an existing iteration will only show good progress made towards meeting the goal
webgate says
Hi Zail
You hit at the core of what a burndown chart is for. It simply shows the amount of work remaining at a given point in time. Used that way, it is useful to us in determining how likely we are to meet our goals. If we want to show things like ‘work added’ or ‘work removed’ then what we have is not a burndown chart but something else.
A name I’ve heard used is an ‘adapted burndown chart’ or ‘alternative burndown chart’. Mike Cohn describes it rather well in his article on the alternative release burndown chart.
Muhammad says
Excellent article Derek. Great answers to questions. Cheers.
Aaron says
“… the customer added in some new user stories …”
This language/workflow does not follow scrum, only the product owner is to add user stories to the backlog.
webgate says
Interesting thought but consider that, while the Product Owner has the final say on content and ordering of the product backlog but they don’t have to create items and they don’t have to be a gate before others add items either.
Sahil says
Hi Derek,
Thanks for the great insights on the burndown chart.
Building upon the above comment,
does it mean that the PO accepted and prioritized the ’10 points’ the customer added in some new user stories …for the next iteration?
webgate says
Yes, that would be the most likely scenario.